Plan Your Equipment Installation

Coordinate equipment, site services, delivery, and commissioning before installation.

Start with your product, throughput, facility layout, and installation location. We will review the ordered equipment and interfaces with your team so the mechanical, electrical, and site requirements can be agreed before installation.

From initial scope to production

  • Define the equipment: agree the product, capacity target, automation, accessories and interfaces in the signed project scope.
  • Plan delivery: confirm shipping arrangements, destination, documentation responsibilities, bill-of-lading dimensions, unloading equipment and the route into the building.
  • Prepare the facility: coordinate qualified local contractors for electrical supply, gas, water, air, drainage, ventilation and fire protection. Confirm local permits and approvals.
  • Confirm readiness: resolve open installation items and agree commissioning dates, trade labor, test product, frying oil, language needs and operating personnel.
  • Commission and train: JDM provides installation supervision and commissioning with customer-provided trade labor unless the signed scope expressly includes it. Agree acceptance criteria and operator/maintenance training.

Fryer oil-handling comparison

Planning parameterJD325CXI referenceJD600 reference
Operating oil volume300 US gal / 1,140 L500 US gal / 1,890 L
Recommended minimum usable oil-tank capacity375 US gal / 1,420 L625 US gal / 2,370 L
JD oil-tank capacity420 US gal / 1,590 L700 US gal / 2,650 L
Oil-tank plumbing and connectionsSame requirements as JD600Same requirements as JD325
Minimum tank capacity uses operating oil volume × 1.25. Confirm the exact ordered model and available receiving volume.

Utility planning reference

ServiceExample planning reference
Electrical serviceTypically 60 A, three-phase for the fry line. Voltage, frequency and included equipment are project-specific. Confirm whether the optional remote blower skid is included in that total.
Burner inputReference combined maximum: 3.8 MMBtu/h (1,100 kW). Operating case: 2.4 MMBtu/h (700 kW). Confirm the ordered burner configuration.
Fuel-gas supply20–50 in. w.c. (5.0–12.5 kPa gauge) at the fryer inlet at required flow. The reference burner-head operating pressure is separately specified as 18 in. w.c. (4.5 kPa gauge).
Compressed air for valve actuationAverage <1 ACFM (28 actual L/min) at 100 psig (6.9 barg), ISO 8573-1 [7:4:4] or cleaner. Air volume is at line pressure. This is not a food-contact air specification.
Filling and cleaning waterRecommended 30 US gpm (110 L/min) at 60 psig (4.1 barg). Cold potable water.
Demister CIP, when fitted8 US gpm (30 L/min) at 40 psig (2.8 barg), for sanitation.
Demister scrubber, when fitted50 US gal/h (190 L/h) at 40 psig (2.8 barg), while burners fire.
Hood exhaust4,000 cfm (6,800 m³/h), with the hood fully lowered for production and cleaning. Combined steam-system backpressure: maximum 2 in. w.c. (500 Pa).
Oil transfer with a JD tankViking AS495 internal gear pump with 2 hp (1.5 kW) motor. Actual flow, head and suction duty require project verification.
Filling/cleaning, CIP and scrubber water duties run separately, without simultaneous use. Steam exhaust and combustion flue are separate systems.

These figures are planning references. The approved project drawings and signed scope define the ordered equipment, final utility requirements and responsibilities.

Dimensions and service access are configuration-specific

Request the approved layout for your ordered machine. One JD500 reference arrangement measures 268 13/16 in. (6,828 mm) in side-view length and 88 9/16 in. (2,249 mm) in end-view width. These are illustrated-configuration dimensions, not universal model footprints or shipping dimensions.

The illustrated retractable hood travels 24 in. (610 mm). Its raised stack height is 150 9/16 in. (3,824 mm). Allow for the ordered hood, ducts, hoses, service access and removal paths. The hood stays fully lowered during production and cleaning. It is raised only for maintenance.

Mechanical cover clearance does not establish electrical working space. Have the qualified project team confirm the complete installation against approved drawings.

Support after commissioning

For this planning reference, remote support extends five years, subject to the signed project scope and applicable programming, service, and travel terms. Wired internet at the control panel and customer IT approval are coordinated for the supplied Phoenix Contact VPN. Customer personnel participate in controlled remote testing.

Use equipment support resources for manuals and replacement-part information. Ask JDM for the current project-specific installation documents.

Confirm these items in your quote

  • Supply voltage, phase and frequency, fuel type and local utility conditions.
  • Destination, shipping and receiving arrangements, and each party’s responsibilities.
  • Required conformity documents and the approvals applicable to the ordered equipment.
  • Included commissioning, training, remote support and any field-service costs.

Start your equipment project

Share your product, target finished output, installation location, and available space. We will discuss the equipment and interfaces your project needs.